Nursery Footbridge
  • Project Nursery Footbridge
  • Location Liverpool
  • Client Birse Rail
  • Value: £250,000.00
  • Date March – April 07’
  • Duration 4 Weeks
  • Accident Free Shifts 208

More Images:

Nursery Footbridge Nursery Footbridge

Project Details

 

The work was to Footbridge no. 38  over the DSE line from Liverpool to Manchester.
 
The spot mileage of the project is 3 miles 15 chains on line reference DSE.
    
8 no. ROR 9 hour possessions had been booked to allow grit-blasting, painting and steelwork repairs to be carried out in-situ.
 
 
But, due to a change in using APB “value engineering” methodology the bridge was lifted off, refurbished and replaced in two 9 hour possessions.
 
This negated the risks of a series of possessions and also limited the potential effect on the environment.
 
 A synopsis of the project is detailed below:
 
·                Establishment of crane including crane pads
 
·                Removal of superstructure
 
·                Full grit-blast and paint to RT98 Specification
 
·                Approximately 4 t of steelwork repairs
 
·                Installation of new steel deck plates
 
·                Application of anti-slip flooring
 
·                Install new bearing pads
 
·                Replacement of superstructure.
 

Shenstone Viaduct


Latest News

  Latest News Railway-bases supply of labour. At the beginning of September 2009 a Labour Supply division was added to the company. This specialises in the supply of high quality trained contractors involved in railway work. Such staff include, Engineering Supervisor (ES), Personal Track Safety (PTS), Crane Controller and Controller of Site Safety (COSS). This service will fulfil the needs of those companies that employ some railway train...Read More